JME maintain all relevant compliances and regulations to ensure that quality is fundamental throughout every stage of our business.

ECA Registered Member

JME are members of the Electrical Contractors Association (ECA) meaning we undergo regular and rigorous technical assessments to ensure compliance with industry regulations. This third party assessment of relevant British and European standards provides our customers with the reassurance that JME are skilled in all areas and provide the safe, high quality and reliable solution expected.

ECA membership also provides a “covered to completion” guarantee that safeguards work of up to £100,000 or 10% of the contract value.

Standards & compliances

JME design and manufacture control panels in line with:

  • BS 7671:2018 IEE 18th Edition Regulations
  • BS EN 61439-1 2011 Low-voltage switchgear and controlgear assemblies – Part 1 General rules
  • BS EN 61439-2 2011 Low-voltage switchgear and controlgear assemblies – Part 2 Power switchgear and controlgear assemblies
  • BS 6739:2009 Code of practice for instrumentation in process control systems: installation design and practice
  • BS EN 60204-1 2006 plus A1 2009 Safety of machinery – Electrical equipment of machines – Part 1 General requirements
  • BS EN ISO 12100 2010 Safety of machinery – General principles for design – Risk assessment and risk reduction
  • BS EN ISO 13849-1 2008 Safety of machinery – Safety-related parts of control systems
  • BS IEC 61000-5-2 1997 Electromagnetic compatibility (EMC)

Our control panels also comply with all current European Standards and ISO requirements, typically ISO 9001, ISO 14001 and OHAS 18001 accreditations.

Documentation

All of our Control Panels come with a comprehensive Documentation Package to suit individual customers needs. Upon hand over, this package could briefly contain the following but not limited to:

  • As built drawings for Control Panel
  • Operation and Maintenance Manuals (1 x paper copy and electronic copy)
  • Declaration of Conformity (CE Marking)
  • FDS
  • Hazop documentation
  • Concept design documents
  • Detail design documents:
    1. Alarm Schedules
    2. Backup and Restoration Procedure
    3. Cable Termination and Check Sheets
    4. Control and Trip System Architecture
    5. Electrical Parts Equipment’s Schedules
    6. EMC Design control plan
    7. Hardware Acceptance Test Specification
    8. Input & Output Schedules
    9. Inspection and Test Plans
    10. Instrument Data Sheets
    11. Instrument Loop Test Procedures
    12. Instrument Schedules
    13. Interlock and Protection Schedules
    14. Panel Fuse Schedules
    15. Plus many more Project management documents
  • Complete and Signed FAT sheets
  • Complete and Signed SAT sheets
  • Certificate of Conformity – Control Panel
  • Declaration of Conformity – Components
  • Drawing Register
  • Parts List with Recommended Spares
  • Technical Data Sheets